Goldwave’s ingenious heavy lifting system creates a breakthrough to turn “impossible mission” to possible solution. In this project, Goldwave design, fabricates and hoists up 5 irregular service decks within extremely compact spacing (from approx. 10-18 meters) from 5th floor to 28th floor to support the construction of a massive concrete transfer slab permanently in place on the 29th floor.

The service decks also serve as safety working platforms for site workers to carry out the remaining works for the transfer slap installation. 5 temporary protection platforms are to be installed as a safety measure to mitigate the risk of falling objects to protect workers during the construction period of service decks.  

SCOPE OF PROJECT  

Design, supply, fabrication and installation (Heavy Lifting)